2004 Barrington Hills
Roads & Bridges Update
Memo to Residents | Table
of 2004 Road Repair Scope | 2004
Road Maintenance Program Presentation (a copy of the presentation
in also available
in PDF, appropriate for printing 981K)
Updates: 8/04 | 8/12 |
8/20 | 9/03 | 9/09 |
9/15 | 9/16 | 9/27 |
10/01 | 10/06 | 10/15 |
11/12 | 11/18
To: Barrington Hills Residents
Subject: 2004 Roads and Bridges Update
Date: July 14, 2004
Dear Fellow Resident:
This letter is to provide you with the first of several updates
on the roadwork that will be along or near your
property. You are receiving this letter specifically because
you may be temporally affected by the roadwork
activities in the next 10 weeks. The attached table shows the
scope and location of the work. Total cost of this
year’s effort is budgeted at $762,000, including $90,000
in motor fuel taxes.
Our intent is to minimize the disturbance to your property,
landscaping, utilities, and travel activities as much as
possible. We are also working to minimize the noise and general
construction impact from the perspective of
being a distraction from our rural lifestyle. Please recognize
that this project, as in year’s past, is a significant
amount of construction work involving heavy machinery, movement
of material, and relocation of traffic. I ask
for your patience while we make these improvements near your
property, and your care while traveling through
and around the construction site. I certainly appreciate the
inconvenience and we will do everything we can to
mitigate the impact.
The new road surface will be very similar in
width and location to the original road. We are not widening
or
relocating any of the original road surfaces. The results will
be very similar to other road projects we have
completed such as Helm and Meadow Hill Roads. These improvements
are designed to minimize the impact on
our rural lifestyle and improve our experience in driving, bike
riding, walking, and horse riding along the
roadways.
The following covers several subjects regarding
the project. Since a wide variety of situations exist along the
construction routes, it’s possible you may have additional
questions or special concerns. Please contact me
directly in this case and I would be happy to assist you.
You can also get frequent road condition and construction updates
on the Barrington Hills WEB site at:
http://www.barringtonhills-il.gov/
I will also post specific road design and budget information.
1. The Work Scope
This year (2003 recap
available online) we
are planning on the following road sections:
• Plum Tree Road – Braeburn to Cuba
• Ridge Road – south of Oak Knoll south towards Lake
Cook
• Cuba Road – various components as part of a multi-year
effort
• Various road repairs, particularly south of Lake Cook
• Inspection and characterization of all bridges and box
culverts in the Village
We are currently expecting to begin work at
the end of July. I will have more information as as get closer
to
construction and the schedule is more firm.
Last year we completed the following road sections:
• Ridge Road -between Oak Knoll and Merri Oaks
• Meadow Hill Road - between Lake Cook and Fox Hunt (but
not the hill)
• Haeger’s Bend Road - between Lake Cook and Chapel
Road
• Church Road
• Algonquin / River Road
We completed this work under the project budget and made maximum
use of our state provided funds which
come from Motor Fuel Taxes. Because we worked so late in
the year, we will have some additional landscaping work to do in
some of these areas. If you still have any outstanding landscaping
or driveway
issues, please let me know.
2. Temporary Road Closures
During portions of the project, the following road segments
will be closed to thru traffic.
Ridge Road will be closed between Oak Knoll and Lake Cook
Update 8/04 August
6th signage will appear in the construction zone, with work
beginning by August 10th.
Update
8/12 Sawcutting of patching and pavement removal began today,
with flaggers providing traffic control. Weather permitting, the
contractor will be beginning the pavement removal/shoulder excavation
and replacement tomorrow, and continuing next week. Signs and flaggers
should be observed through the construction zone.
Update
8/20 The bituminous base course widening and patching was completed
on Friday. The contractor anticpates placing level binder
on Tuesday, and
projects the placement of the final surface by the end
of the week.
Update
9/03 The petromat and final surface has been
in place since Wednesday, September 1. The binder was completed the previous week.
Placement of aggregate shoulder was completed Thursday September 2nd.
Final landscaping (topsoil, seed, and blanket) will begin after Labor Day.
No work will occur over the holiday weekend.
Update
9/09 The landscaping (topsoil, seed, and blanket) is
complete. Once the seed has started to germinate the Village
Engineer will prepare a punchlist to close out the project.
Plum Tree Road will be closed
along various sections, notably the hill and intersection approach
east of Ridge
Road.
Update 8/04 August 9th signage
will appear in the construction zone with work beginning
by August 16th. Surveyor flags will be seen throughout the project
area
denoting utilities, elevation and points of reference to the
plans.
Construction is expected to take six weeks.
Update 8/20 The contractor
has scheduled
the sawcutting to begin on Monday August 23rd. Construction
staking has begun on the east end of Plum Tree and will continue
throughout
the week.
Update 9/03 The saw cutting will continued
throughout the week and was completed by Thursday September 2nd. The contractor will resume
working after Labor Day. No work will occur over the holiday weekend.
After the holiday the silt fencing will be installed and the contractor
expects to begin patching operations on Wednesday September 8, 2004.
Update 9/09 The contractor will begin patching operations and
it will extend into the follwing week. No road closures are scheduled yet, but should be
expected for the excavation for the storm sewer and work at the eastern end
near the hill. Traffic control signs and flaggers should be observed through out the construction zone.
Update
9/15 The contractor is continuing patching on Plum Tree Road, and anticipates that patching
will be almost complete by the end of the day. Once the patching is complete the pavement removal and shoulder
excavation will begin for the base course phase of the construction.
Update
9/16 The contractor has completed the patching on Plum
Tree Road. Begining on Monday 9/20 will be the construction
of the storm sewers and culverts, starting with driveway
culverts.
This phase of
the construction will require the temporary closure of the
road on Tuesday 9/21 and Wednesday 9/22, because several
of the culverts cross the full width of the road. Notification
will begin this week to the school bus companies and Algonquin
Township Highway Department and Fox River Grove as the other
road jusridictional authorities in the area. Watch for the
detor signage on Monday September 20th.
The contractor may require a road closure in a few weeks for a period of 8
to 10 days to accommodate excavation and construction around the hill in the
area roughly 800 feet west of Ridge Road.
Update 9/27 The
contractor will continue for the entire week the excavation of the
edge of pavement and
shoulder. Patching of the culvert trenches begain today.
On Monday, October 4th further closures will occur
of Plum Tree Road and lasting two weeks. Work will occur in the area of
the large hill, roughly 800 feet west of Ridge. Specific information on
the progress will be available through the office of the Village Engineer
(847-478-9700, Mike Lukich) to residents, Algonquin Township, Fox River
Grove and the bus companies.
Update 10/1 The road will be closed to through traffic from Monday, October
4th to Friday October 15th during the construction in the area of the hill
which is approximately 800 feet west of Ridge Road.
During this time all driveways located west of
650 Plum Tree should exit west to Algonquin Road, and all driveways east
of 650 Plum Tree should exit east to Ridge Rad. Signage and flagers will
give direct information during construction.
Day to day updates or questions may be directed to the resident engineer at
847-344-4482.
Update 10/6 The
contractor continues throughout the remainder of the week to place the
base course layer on the north side of the road, and intends to complete the
entire length by weeks end. On Friday October 8th the contractor will resume
excavation of the designated areas on the south side of the road.
Thereafter the concrete subcontractor is expected to begin forming and
placing the
curb, and all of the curb is expected to be in place by the end of the
day on Monday October 11th.
Miscellaneous patching is expected to occur at the same time on Meadowhill,
Chapel, and Cuba roads.
Update 10/15 At
the conclusion of work on Friday October 15th the contractor will re-open
Plum Tree Road to thru traffic Work will continue on the roadway and drivers
are advised to exercise caution. UPDATE 10/15 Posted
4:00 PM - The
contractor was unable to complete the work and Plum Tree Road remains
closed to thru traffic.
Update 11/12 Final
surface was completed this week on Plum Tree. On Monday November
15th, the
stone shoulder will be placed on the south side of the road, and Tuesday
the ditching will be completed. Landscaping is scheduled to begin on
Wednesday or Thursday of next week.The road remains closed to through
traffic until the completion of the shoulder work. Local traffic during
construction to adjoining homes is possible upon direction of the contractor
and roadside signage. Caution still should be exercised in the work zone.
Update 11/18 The contractor
has completed the rough grading and the roadway has been re-opened to through traffic. There will be remaining work
by the contractor which includes final landscaping. Caution still should be exercised by all drivers.
Local and emergency traffic will always be allowed
through. These road closures are necessary because the
poor condition of the original pavement sections and the
narrow area in which the construction crews are to
work. In order to protect the safety of the construction crews
and people traveling on the roads, it was
determined that the best course of action is to close certain
roads sections during a portion of the project. While
road closures are an inconvenience to our residents, it will
help to speed up the construction schedule allowing
us to return the roads back to normal service sooner. Most
of the closures will only last a few days at a time.
We are working to schedule to closures so that
they do not happen simultaneously. We will provide additional
information on the road closure schedule, and detours will
be well marked in advance of the closure.
3. School Bus Pick-Up
We will be in contact with Barrington Transportation
Company and we will be coordinating with them regarding
the temporary roadway closures. You will receive additional
notification of any changes in school buss pickup.
Barrington Transportation Company can be reached at 847-381-1043.
Update 9/16 In regards to the temporary closures of Plum Tree
Road, those persons
in Fox River
Grove School District #3, may contact John Hill (Superintendent &
Transportation coordinator)
at 847-516-5100 (Phone).
4. Stakes and Markings
Some of you may notice stake markings along
the construction routes set back some distance from the existing
road surface. In the past people have misinterpreted these
as the location of the new roadway. This is NOT the
case. These markings are set back away from the work area to
provide stable reference points for the
construction work; they are not representative of actual pavement
location.
5. Landscaping, Mailboxes, and Driveway Aprons
We have been taking photos and documenting the
landscaping, driveway aprons, mailboxes, and other signage
along the construction route. We are always very conscious
of these elements during construction. However,
some disturbance is inevitable during this kind of project.
We are committed to returning your landscaping
elements to their original condition by the end of the project.
If you plan on moving your driveway or making
other significant changes regarding your property as it adjoins
the roadway, this would be a good time to bring it to our attention.
By coordinating our efforts, we can avoid
confusion and lower the costs of the work both to you and to
the Village.
For those of you interested in driveway paving, or upgrades
to private roads, we can put you in touch with our
contractors. While the Village does not pay for these services
for you, you might find you can get a good price
since the work can be coordinated with adjoining Village activities.
A number of residents have taken advantage
of this in the past.
I believe you will find that the new roadways
will be a substantial improvement over past conditions. If you
have any further questions, please give me a call at 847-381-8174
or e-mail at Bob@RGALabs.com; or our Village
Manager, Bob Kosin, at 847-551-3004.
Sincerely,
Robert G. Abboud
BH Village Trustee
Chairman Roads & Bridges
13 Country Oaks Lane
Barrington Hills, IL 60010
Bob@RGALabs.com
Home: 847-381-8174
Office: 847-381-1932
Cell: 847-921-1932
Village of Barrington Hills 2004 Road Repair
Scope
July 14, 2004
| Module |
Road Name |
Effort |
Length
in Mi |
| 1 |
Plum Tree |
Reconstruction |
1.24 |
| 1A |
Plum Tree - West |
Reconsturction |
0.07 |
| 2 |
Ridge Road |
Reconstruction |
0.40 |
| 3 |
Plum Tree Road |
New surface repair |
0.36 |
| Sping Creek Road |
New surface repair |
0.49 |
| 4 |
Heagers Bend |
Striping |
2.01 |
| Helm Road |
Striping |
0.91 |
| Ridge Road |
Striping |
2.00 |
| 5 |
Chapel Road |
Patching & Structural |
1.00 |
| Cuba Road |
Patching & Structural |
0.71 |
| Healy Road |
Patching & Structural |
0.73 |
| 6 |
Abeerdeen Road |
Cul-du-sac replacement |
|
| Three Lakes Road |
Culvert replacement |
|
| Oak Knoll Road |
Field tile replacement |
|
| Meadow Hill Road |
Ditch work |
|
| 7 |
Aberdeen Drive Repairs |
General repairs |
|
|